By Anton Riecher
Medina County Commissioners Court voted Monday to approve a preliminary plat for the proposed $28 billion El Camino data center and power infrastructure project southwest of Devine, in a unanimous vote by Danny Lawler, Larry Sittre, David Lynch, and Jessica Castiglione.
To be located on a 525-acre site Highway 132, the data center campus will consist of eight to nine buildings requiring 800 megawatts of electrical power to operate. That power will be provided by the data center’s own electrical substation and natural gas plant.
Ryan Nuckolls, a founding partner of Texas Energy Group, introduced his firm as the “horizontal development company” spearheading the project in Medina County. He detailed plans for the site including access, drainage, water and sewage.
“As far as the ingress/egress we have been in full compliance with TXDot,” Nuckolls said. “It will be a 40-to-60 foot entrance with concrete culvert drainage. The road inside the facility will be 20-to-30 foot paved for any type of emergency vehicle to easily access.”
A second entrance will be located on the north side of the campus off FM 2200, he said.
The submitted plat includes detention ponds, Nuckolls said. However, since no impervious cover to block or prevent natural infiltration of water into the soil is proposed at this stage, drainage calculations were not included in the application.
Stormwater control will be addressed once impervious cover is defined in the final plat, he said.
Industrial agreements for water supply have been negotiated with Yancey Water Supply Corporation, Nuckolls said. Cooling for the electrical equipment involved will be provided by a closed-loop system which will be required by state law within the next several months.
A one-time fill of about 1 million gallons should last about 15 years at a two percent evaporation rate, Nuckolls said. That amount is equivalent to the annual use by 18 homes or one McDonald’s restaurant.
Nuckolls said there would be handled by on-site facilities with no discharge to the nearby city sewer system. The buildings on site will be of tilt-wall construction with spray-foam insulation. He also said the company has met with local fire officials about training and support.
Mico resident Debra Roach took the podium to speak against…LOGIN TO CONTINUE READING at www.devinenewsmembers.com. You will get instant access to our full E-edition, and begin getting the newspaper delivered to your home next week for $42 a year in Medina County. Support important local city, county, and school news like this!

Mico resident, Debra Roach, addresses the Medina County Commissioners Court with concerns and questions about the data center development.